Reset Actions
Sub InitialisePreStart()
;--- Logic executed very early before first iteration
; Perform complete reset of project
["$Solver.Cmd.CompleteReset"] = 1
EndSub
|
Activate/deactivate flowsheets
Note: Separate tags for Activate / Deactivate. These cannot be set to 0.
Sub InitialisePreStart()
;--- Logic executed very early before first iteration
; Activate flowsheet 05_Flowsheet
["PlantModel.Page[05_Flowsheet].Activate"] = 1
; Deactivate flowsheet 10_Flowsheet
["PlantModel.Page[10_Flowsheet].DeActivate"] = 1
EndSub
|
Cross-page connections
Sub InitialisePreStart()
;--- Logic executed very early before first iteration
; Turn on cross-page connection in Feeder XPG_001
["XPG_001.ConnectionOn"] = 1
; Turn off cross-page connection in Feeder XPG_002
["XPG_002.ConnectionOn"] = 0
; Set cross-page connection in Feeder XPG_001 to XPG_002
[str "XPG_001.Conn_To"] = "XPG_002"
EndSub
|